Surface Finishing & Pre-treatment
Polishing Technician - Junior

Surface Finishing & Pre-treatment

Surface Finishing & Pre-treatment Masterplan (QLQ System)

Goal: Transform raw die-castings (Zinc) and stamped parts (Iron/SS) into smooth, mirror-like surfaces ready for high-end plating.

Scope: Deburring (Deflashing), Smoothing, Fine Polishing, and Ultrasonic Cleaning.

Sourcing Strategy:

  • Equipment (Tumbling Machines): [Purchase Locally / Recommended Suppliers].

  • Consumables (Media/Stones): [Purchase Locally] (Ceramic, Plastic, Porcelain, Corn Cob).

  • Chemical Compounds (Grinding Fluids, Polishing Pastes): [QLQ Product] (Crucial for speed and brightness).


Phase I: Process Flow & Equipment Selection

1. Zinc Alloy (Zipper Pulls, Buckles)

  • Characteristics: Soft metal. Easy to deform. High requirement for surface smoothness.

  • Recommended Equipment: High-G Centrifugal Disc Finisher (for speed) or Vibratory Bowl Finisher (for delicate parts).

  • The 3-Step Process:

    1. Coarse Grinding (Deflashing): Removing parting lines and burrs.

    2. Fine Polishing (Smoothing): Closing surface pores and creating a semi-bright finish.

    3. Ultrasonic Degreasing: Removing polishing wax/paste residue.

2. Iron & Stainless Steel (Buttons, Rivets)

  • Characteristics: Hard metal. Burrs are sharp and difficult to remove. Iron rusts easily during tumbling.

  • Recommended Equipment: Rotary Barrel Tumbler (aggressive) or Vibratory Bowl.

  • The Process:

    1. Heavy Deburring: Aggressive cutting.

    2. Burnishing: Using steel media to peen the surface for brightness.


Phase II: Detailed Operational SOP

Step 1: Deburring / Cutting (Rough Finishing)

  • Objective: Remove die-casting flash (Zinc) or stamping burrs (Iron/SS).

  • Media Selection:

    • Zinc: Resin bond cones (Plastic Media) – Gentle cutting.

    • Iron/SS: Ceramic triangles (Fast cutting).

  • Chemicals:

    • [QLQ Product] Heavy-Duty Grinding Compound: Accelerates cutting and keeps media clean.

  • Operational Details:

    • Ratio: 3 parts Media : 1 part Workpieces (by volume). Never overload workpieces or they will hit each other.

    • Water Level: Just covering the load (Vibratory) or 50% level (Rotary).

    • Time: 2–4 hours (depending on burr size).

    • QC Check: Visual inspection under 10x magnification. No visible parting line allowed.

Step 2: Fine Polishing / Lustering

  • Objective: Turn the matte surface into a glossy, smooth surface (Ra < 0.1µm).

  • Media Selection:

    • Zinc: High-density Porcelain balls (White) or Zirconia beads.

    • Iron/SS: Stainless Steel balls (Satellite/Ball mix) for burnishing.

  • Chemicals:

    • [QLQ Product] High-Gloss Polishing Liquid: Provides lubrication and chemical brightening.

    • [QLQ Product] Anti-Rust Compound (For Iron only): Mandatory to prevent flash rusting during the process.

  • Operational Details:

    • Time: 30–60 minutes (Centrifugal) or 2–3 hours (Vibratory).

    • Critical Note: The water must flow through continuously (Flow-through system) to flush out dirt, OR be changed every cycle. Dirty water = Dull finish.

Step 3: Drying (Optional but Recommended)

  • If parts are not plated immediately, they must be dried.

  • Method: Heated Vibratory Dryer using Corn Cob or Walnut Shell grit.

  • Chemicals: Add [QLQ Product] Polishing Paste to the corn cob to add a final "Jewelry Wipe" effect.

Step 4: Pre-Plating Cleaning (Ultrasonic)

  • Note: Even after tumbling, parts have polishing residue and microscopic dust.

  • Equipment: 3-Stage Ultrasonic Cleaning Machine.

  • Chemicals:

    • [QLQ Product] Ultrasonic Wax Remover: Specifically dissolves the binders in polishing compounds.

  • Process:

    • Tank 1: Ultrasonic Clean (60°C, 5-10 mins).

    • Tank 2: Ultrasonic Rinse (50°C).

    • Tank 3: Pure Water Spray.


Phase III: Quality Control & Inspection Standards

Before sending parts to the plating workshop, the "QC Gate" must check:

  1. The "White Cloth" Test:

    • Wipe the part with a clean white cloth after ultrasonic cleaning.

    • Pass: No black or grey residue.

    • Fail: Residue indicates poor ultrasonic cleaning $\rightarrow$ Will cause peeling in plating.

  2. The "Finger Nail" Test (Deflashing):

    • Run a fingernail across the parting line/edge.

    • Pass: Smooth transition.

    • Fail: Nail catches on a burr $\rightarrow$ Will cause "High Current Density Burning" (roughness) during plating.

  3. Water Break Test (Degreasing):

    • Dip part in water and remove.

    • Pass: Water film covers the surface continuously for 30 seconds.

    • Fail: Water beads up like on a waxed car $\rightarrow$ Oil is still present.


Phase IV: Expert Maintenance Tips (Preventing Common Failures)

  1. Media Grading:

    • Stones/Media wear down and get smaller. Small stones can get lodged/stuck in the holes of zipper pulls or buttons.

    • Action: Screen/Sieve the media weekly to remove undersized stones.

  2. Compound Concentration:

    • Using too much [QLQ Product] Polishing Liquid is wasteful; using too little causes media glazing (stones stop cutting).

    • Action: Use an automatic dosing pump (e.g., 50ml every 15 mins).

  3. Iron Rusting:

    • Iron buttons can rust inside the polishing barrel if the pH drops.

    • Action: Ensure [QLQ Product] Anti-Rust Compound keeps the solution pH > 9.0.

Surface Finishing & Pre-treatment Example zinc-alloy hardware route: ultrasonic degreasing, hot and cold rinses, brief weak-acid activation, cold rinse, then copper strike and nickel finishing. Cleaning at 60 degrees Celsius for five minutes; activation with 1 to 2 percent sulfuric acid for 15 to 30 seconds; nickel bath at 50 to 60 degrees Celsius. Validate chemistry with the supplier before production. Surface Finishing & Pre-treatment Zinc-alloy hardware / example wet-process route PROCESS SKETCH / 28 Rack transfer 01 / Degrease 02 / Rinse 03 / Activate 04 / Rinse 05 / Finish Ultrasonic clean Bath: 60 °C Dwell: 5 min Hot water rinse Then cold rinse Separate tanks Weak-acid dip H₂SO₄: 1-2% Dwell: 15-30 s Cold water rinse Keep surface wet No drying delay Copper strike first Then nickel bath Nickel: 50-60 °C CONTROL: Avoid over-etching; confirm chemistry and dwell on trial parts. NOT TO SCALE / Rinse and finishing tanks grouped for clarity
Example zinc-alloy hardware pre-treatment and plating route, with cleaning, activation and nickel-bath controls. Validate settings for the alloy and supplier chemistry. Source: QLQ knowledge base, Zinc-Alloy Plating Defect Analysis and Treatment Solutions (updated 2026-07-28).
Polishing UnitJUNIORSurface Finishing & Pre-treatmentOperatorMedia under 3 mm polishes nothing - check the sieveevery batch.ChemistCompound 1-2% by weight. More compound means moreresidue, not more shine.QCJudge gloss under a 60 degree light, never by eye indaylight.ManagerMedia cost per kg of parts is the number to watch, notmedia price.STEP 1Load & InspectGrade max 2Sort defects30 kg/batch1STEP 2Whirlpool PolishMedia 3-6 mm40-60 minWet slurry2STEP 3Barrel Polish25-40 rpm30-50 minCompound 1-2%3STEP 4Rinse & SeparateSieve 2 mmRinse 2 minReclaim media4STEP 5Dry & Visual QC70-80 CGloss checkNo carry-over5!Over-running rounds the sharp edges - mirror finish turns blurry.COMMON MISTAKES vs WHAT WORKSfrom shop-floor auditsxRun media until parts look shinyv40-60 min, then sieve and check media sizexMore compound means more glossv1-2% by weight; excess leaves residuexJudge gloss in daylightvCheck under a 60 degree light30 kgBatch40-60 minRun time300-400 hMedia lifeCASE FROM THE LINECase: orange-peel batches traced to polishing media worn below 3 mm.QLQ Surface Treatment | steps, roles, checkpoints, mistakes and a real case
Polishing Unit - process board with operator, chemist, QC and management notes, mistakes and a case.

FAQ - Surface Finishing & Pre-treatment

Straight answers from the shop floor. Ask us on WhatsApp if your case is different.

How do I prepare the parts before this step?
Goal: Transform raw die-castings (Zinc) and stamped parts (Iron/SS) into smooth, mirror-like surfaces ready for high-end plating. Scope: Deburring (Deflashing), Smoothing, Fine Polishing, and Ultrasonic Cleaning.
What is the step-by-step procedure?
1. Zinc Alloy (Zipper Pulls, Buckles) Characteristics: Soft metal. Easy to deform. High requirement for surface smoothness. Recommended Equipment: High-G Centrifugal Disc Finisher (for speed) or Vibratory Bowl Finisher (for delicate parts).
What daily checks keep this process stable?
Before sending parts to the plating workshop, the "QC Gate" must check: The "White Cloth" Test: Wipe the part with a clean white cloth after ultrasonic cleaning.
Surface Finishing & Pre-treatment
Surface Finishing & Pre-treatment - Goal: Transform raw die-castings (Zinc) and stamped parts (Iron/SS) into smooth, mirror-like surfaces ready fo

Quick reference - what to check and why

StageWhat it means on the line
Surface Finishing & Pre-treatment Masterplan (QLQ System)Goal: Transform raw die-castings (Zinc) and stamped parts (Iron/SS) into smooth, mirror-like surfaces ready for high-end plating.
Phase I: Process Flow & Equipment Selection||H4|| 1.
Phase II: Detailed Operational SOP||H4|| Step 1: Deburring / Cutting (Rough Finishing) Objective: Remove die-casting flash (Zinc) or stamping burrs (Iron/SS).
Phase III: Quality Control & Inspection StandardsBefore sending parts to the plating workshop, the "QC Gate" must check: The "White Cloth" Test: Wipe the part with a clean white cloth after ultrasonic cleaning.
Phase IV: Expert Maintenance Tips (Preventing Common Failures)Media Grading: Stones/Media wear down and get smaller.
FAQ - Surface Finishing & Pre-treatmentStraight answers from the shop floor.
Barrel Plating Workshop for Zinc Alloy Products